Client:
MACA Interquip Construction Pty Ltd
Location:
King of the Hills is located 80 km south of the Red 5’s Darlot Gold Mine and 28 km north of the town of Leonora in the Eastern Goldfields Region of Western Australia
Type:
Greenfield
Capability:
Engineering Design, Project Services
Mintrex Scope:
Engineering design services for the process plant (excluding the grinding and classification) and associated plant services.
Throughput:
4 Mtpa
Commodity:
Gold
Mintrex is delighted to have delivered our design scope for the MACA Interquip Pty Ltd (MIQ) King of the Hills (KOTH) Process Plant EPC project. KOTH is owned by Red5 and located 80 km south of their Darlot Gold Mine in the Eastern Goldfields region of Western Australia.
Design of the process plant, excluding the grinding and classification area, formed the Mintrex scope and our proven gold plant designs were key to our successful delivery.
Fabrication and construction are well underway and Mintrex will continue to support MIQ and Red 5 in an informal capacity, wishing the team well with this exciting project.